Eko Electricity Disco Announces 5-weeks Planned Power Outage That'll Affect Lagos Island, Ajah & Lekki

According to statement released on Facebook by the Eko Electricity Distribution Plc, there'll be a planned power outage at Ajah T/S, specifically Ajah-Egbin line 3 & 4 to enable lines crew replace corroded disc insulators on the lines.

The statement says, 'the outage will affect all the 33kV feeders emanating from Ajah, Lekki and Alagbon T/S. This outage is slated to commence on the 21st of November, 2017 (tomorrow) and it is scheduled for every Tuesday and Thursday weekly for 5 weeks. Also, the outage duration is 4 hours per day'.